Yinson’s FPSO Helang achieve first gas


Dateline 2019-12-18, NST:

 Yinson Holdings Bhd’s latest floating production, storage and offloading (FPSO) vessel – FPSO Helang, has successfully completed performance testing, and charter rates commenced on 6 December 2019.

The Yinson team achieved timely delivery of first oil production 19 months after signing the contract for delivery of the FPSO facility with client JX Nippon Oil & Gas Exploration (Malaysia) Ltd (JX Nippon).

Yinson group chairman Lim Han Weng said the achievement was made possible through the great teamwork between the Yinson team, client and subcontractors.

“I would like to thank JX Nippon and Petronas for the opportunity to undertake this project.

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: