Exco: RM180m Perak gas pipeline ready by end of year


Dateline 2019-04-22, Malay Mail:

The 140km gas pipeline project from Ayer Tawar to Lembah Kinta in Perak will be completed by the end of this year, the state assembly heard today.

State Investment and Corridor Development Committee chairman Datuk Seri Mohammad Nizar Jamaluddin said development and installation of the gas pipeline project were beyond the two-thirds mark.

“The project has seven packages, which involves three districts namely Manjung, Perak Tengah and Kinta.

“And as of February 28, about 67.7 per cent has been completed,” he said.

The Sungai Rapat assemblyman said that the RM180 million gas pipeline project would benefit 44 manufacturing companies.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: