Inside gossip says that the original schedule was unrealistic anyway, so I guess the ‘delay’ is of interest to those who aren’t into reading inside-baseball analysis.
Dateline 2012-10-30:
The commercialisation of Petronas Gas Bhd‘s liquefied natural gas (LNG) regasification terminal (RGT) in Sungai Udang, Malacca may be postponed to early next year due to the delay in engineering, procurement and construction (EPC) .
“We gather from various industry sources including the contractors that the RGT could be operational by end-Jan 2013 instead of end-2012.
“This is a one-month delay versus Petronas Gas’s guidance of end-2012 and a five-month delay from the initial start date of Aug 2012.
“We believe that the delays are not due to Malaysia’s regulatory reforms but the result of EPC challenges,” CIMB Research said.
…